The project will improve the soil profile, enhance drainage times and reinvigorate the visual aesthetic of the entire green.
Feb 19, 2016
CONSTRUCTION DETAILS:
- Start Date: February 15, 2016
Normal Working Hours: 7am-5pm. Weekend work will only be necessary if there are major rain delays.
- Anticipated End Date:
-
- May 15, 2016 (construction complete but fencing will remain until turf root structure is stable)
Campus Detours or Interruptions:
Fencing will completely surround Tech Green through the duration of the project. Along the sidewalk of the north side, pedestrians will be restricted to five feet of walking area. Food trucks will be relocated. Tech Green is to remain fenced through the colder months to promote root zone stabilization.