The improvements will refresh existing vegetation and restore the quality of landscape and hardscapes alike. A new seating area will be installed behind the Corliss pump.
Feb 01, 2016
The improvements will refresh existing vegetation and restore the quality of landscape and hardscapes alike. A new seating area will be installed behind the Corliss pump.
- New bike racks in front of Tech Tower
- Several additional benches
- Updated shrubbery and vegetation
- Brick pavers on Cherry Street will be added after library construction
- Sitting/study area with tables and chairs for at least 28 people will be available behind Corliss pump
CONSTRUCTION DETAILS:
- Start Date: March 1, 2016
Normal Working Hours: 7am-5pm. Weekend work will only be necessary in there are major rain delays.
- Anticipated End Date: July 31, 2016
Campus Detours or Interruptions:
Vehicular access will be allowed during construction. However, there will be road closings for through traffic. The map included here indicates locations of construction, road closings, pedestrian access, bus stops and ADA accessible entrances.